Corrugated Installation Notes:--> Corrugated Quote & Order-------Reload Site
-.
Roof Purlin spaced every 36" at ridge & gutter, 48" at mid spans.
Wall Purlins (girts) spaced every 4-5 ft.
Overlap: When joining sheets in a horizontal run, an overlap of one corrugation is recommended and yields an overall coverage of 48" see Sheet Joining. When doing a long roof, or vertical run, with more than 1 sheet, the upper sheet in the overlap should be in the up-wind direction. If an overlap is needed in the sheet length, such as this, we recommend a 6" overlap. Pop Rivets may be used to achieve a even fitting and watertight joint. Position Pop Rivets every 12" along the overlap.
Sealants: Do not apply sealants between overlapping panels, as this will cause unsightly dirt streaks. Silicone may be used in areas where two sheets meet at an angle, such as the intersection of vertical sheets and roof sheets.
Screws: See Screw Layout and notes below to determine screw count.
Ridge Flashing: To seal the pitched roof from the elements, install a ridge cap. This cap may be fabricated from sheet aluminum or galvanized steel. Horizontal closures required when using sheet metal flashings. See Ridge Details
Horizontal Closures: These foam rubber closures should be used at the upper and lower edge of the sheet (in heated spaces), to seal from the weather and air infiltration.