- Metal Bldg. Corrugated Store &
Install --Corrugated
Quote and Order
-
- Storage: Store in dry, shaded,
well ventilated area. Supported, sloped stacking best. Store
sheets in covered areas, but not under flexible PVC
coverings.
- Sheet Orientation Warning: One
side of sheet has protective U.V. surface, this surface must be
facing to exterior. Sheets covered with plastic film and marked
exterior side. Prior to install peel film off sheet.
- Cutting: Circular saw with
plywood blade or jig saw with fine tooth blade. Clamp to avoid
vibration. Leave film on sheet until ready to install.
- Sheet Positioning: Install
polycarbonate sheets with corrugated ribs running vertically on
walls, and with slope on the roof.
- Sheet Install: Install in
similar fashion as adjoining steel panels.
- Overlap: Overlap of 1
corrugation recommended and yields an overall coverage of 36". If
an overlap is needed in the sheet length, we recommend a 6"
overlap. Pop Rivets may be used to achieve a even fitting and
watertight joint. Position Pop Rivets every 12" along the overlap.
Do not apply sealants between overlapping panels, as this will
cause unsightly dirt streaks.
- Procedure: Begin by installing
roof sheet. Wall sheets installed butt against roof panels. Sheet
metal flashing is installed after sheet is in place. Corner Trim
may be used, see Hardware.
- Horizontal Closures:
See
drawings to determine In & Out Quantity.
- Attachment: Fasten screws snug.
Do not over tighten. Predrill with 1/4" bit to allow for
expansion. See
Layout
and Screw Positioning Guidelines.
-
- Cleaning: Clean with warm, soapy
water. If any dirt remains wipe with soft cloth. Do not scrub,
scrape or use solvents. Rinse and dry with soft
cloth.
-
-